Finishing ( completing) standards

 

1. Foundations - ( the price does not include making the foundations )

  • reinforced strip foundations ( concrete C20/25, reinforcing steel A-III)

  • foundations walls made of concrete blocks

  • levelling layer ( concrete C8/10)

  • vertical water insulation

  • horizontal water insulation (bituminous coat)

2. 1.Exterior walls

The structure of exterior walls ( by rotation from inside):

  • 12,5 mm plaster/gypsum board (drywall) putted, painted to white

  • 100 mm bearing (load) construction from glued laminated timber in HBE system

  • 160 mm mineral wool, three layers

  • 2 mm reinforced mineral stucco in white colour

3. Internal walls

The structure of internal walls:

  • 12,5 mm plaster/gypsum board (drywall) putted, painted to white

  • 80/100 mm bearing (load) construction from glued laminated timber in HBE system

  • 12,5 mm plaster/gypsum board (drywall) putted, painted to white

4. Joining the semi-manufactured components.

All of the elements are joined together with help of special steel forging and screws which make the construction stiff. The walls are joined for good to the foundations by using the steel connectors.

5. Ceiling construction

The structure of ceiling construction ( by rotation from the bottom):

  • Glued laminated timber ceiling in HBE system

  • 50mm Styrofoam EPS100

  • Ceiling installation

  • Polythene foil

  • 50 mm monolithic concrete jastrych

6. Roof construction

The roof constructions are made of glued laminated timber or glued timber KVH.

The structure of the roof with using the concrete tile from the top:

  • Concrete tile

  • Impregnated wooden battens and counter-battens

  • Wind insulation with high steam permeability

  • 200 mm bearing ( load) construction made of glued laminated timber or glued timber KVH

  • 200 mm mineral wool

  • Steam insulation foil

  • Impregnated wooden battens

The roof structure with using asphalt shingle (tile) from the top:

  • Asphalt tile/ top asphalt roofing with topping

  • The base asphalt roofing layer

  • 18 mm panel osb3

  • Wind insulation with high steam permeability

  • 200 mm bearing ( load) construction made of glued laminated timber or glued timber KVH

  • 200 mm mineral wool

  • Steam insulation foil

  • Impregnated wooden battens

7. Roof drainage

Waterspouts and drainpipes are made of high quality synthetic material with UV radiation protective coating , which prevents from colours fading. The drainpipes are stuck in rain installation.

8. The windows and balcony doors

All the windows and balcony doors/ terrace doors are made of glued timber. The windows are the tilt-turn windows.
Outside windowsills are made of duromarble
Inside windowsills are made of glued laminated timber
All the window-panes and French doors? panes have two layers structure with heat permeability coefficient U=1,1W/m2K

9. Outside doors

Front doors- GERDA, steel, equipped with 3 anti-bribery forging points.

10. The floors

The floors layers of the ground floor from the top:

  • 50 mm monolithic concrete jastrych

  • Polythene foil

  • Installations circulated In the ceiling

  • 100mm Styrofoam EPS100

The floors layers of the loft ( attic) from the top:

  • 50 mm monolithic concrete jastrych

  • Polythene foil

  • Installations circulated In the ceiling

  • 50 mm Styrofoam EPS100

11. The central heating system

It is made of Pex Al pipes in a separatory system. The pipes have aluminium insert and an anti diffusive layer. Every pipe is conducted to the radiator in one section, without any redundant connections in the floor. Such a system is the safiest because in case of a breakdown there is a possibility to turn off each of the elements separately.

12. The chimneys.

The fumes system chimneys made of concrete blocks. The chimneys of ventilation system are also made of concrete blocks or in PCV system. Above the hipped roof end the chimney is plastered. On the roof there are some steps for chimney sweeper leading to smoke chimney.

13. Water and sewage installation

Water and sewage installation is made of PCV pipes. Water installation will be made in PP system of PN- 20 pipes (resistance welded polypropylene). At present it is the safiest system used to water installations.

14. Electrical installation

The electrical installation is complete and it includes distributing the electrical installation all over the house. What is more, there is also a 36 modules distribution board.

15. Building documents

We offer to adapt every project to a detailed design if a client needs it.

16. Transport costs.

The costs of the transport are included in the price of the house.

17. Other arrangements.

Detailed arrangements and suggested changes are usually agreed during signing the contract for a house in HBE system.